Excavation Calculator – Bank m³ & Truck Loads

Quick answer

Excavation calculator converts pit and trench volumes to loose m³ (clay +30%, sand +12%), then truck loads at 10-14 m³ per dump run.

Figures are estimates from this calculator’s standard formula — adjust the inputs in the tool below for your exact number.

How does the excavation calculator work?

Loose Volume = Bank Volume × (1 + Swell %); Loads = Loose m³ ÷ Truck m³

Excavation math has two volumes: the bank volume you dig (pit length × width × depth, plus side slopes on deep digs) and the loose volume you haul, after the soil swells - clay expands about 30%, sand 10-12%, mixed ground 20-25%. Trucking is priced on loose cubic meters: a standard dump truck carries 10-14 m³, a tri-axle up to 20. Worked example: a 10 × 8 × 1.5 m basement pit is 120 m³ bank; in clay that swells to 156 loose m³ - thirteen 12 m³ truck loads. Always separate topsoil (10-30 cm, reusable), and check OSHA-style sloping or shoring before anyone enters a trench over 1.5 m deep.

  1. 1

    Take dimensions

    Note the pit dimensions and soil type for the area you are covering or filling.

  2. 2

    Run the calculation

    The calculator applies Loose Volume = Bank Volume × (1 + Swell %); Loads = Loose m³ ÷ Truck m³ the moment you type.

  3. 3

    Check the breakdown

    Compare base quantity and waste-adjusted totals side by side.

  4. 4

    Plan the purchase

    Use the final figure to price and schedule the delivery.

Use Cases

Gravel and sand supply

Ton and m³ figures for excavation deliveries.

Landscape leveling

Topsoil and mulch depths for excavation finished grades.

Cut and fill balance

Balance excavation cut against fill to minimize hauling.

Common Mistakes

  • Compacting thick lifts

  • Forgetting stripping topsoil

  • Under-ordering by truck

FAQs

How many truck loads for 100 m³ of excavation?

Loose 130 m³ in clay → 11 loads at 12 m³; bank-volume thinking books 8 and stalls the site.

Soil swell factor by type?

Clay 25-40%, sand 10-15%, gravel 12-15%, rock 50%+ - hauling costs follow the loose number.

How much does a dump truck carry?

10-14 m³ standard, 14-18 tandem, 16-20 tri-axle - and topsoil loads settle 10% in transit.

Weight of excavated soil?

1,600-1,900 kg per bank m³, up to 2,100 wet - legal axle limits cap loads before volume does.

Safe trench slope without shoring?

OSHA runs 0.5:1 in type A soil, 1:1 type B, 1.5:1 type C; beyond 1.5 m depth, slope it or shore it.